Inspection and test plan template

Twenty plans, already written, with the acceptance criteria filled in — the ones this app ships with, from substructure and drainage through to testing and commissioning. Download the Excel file, or read the whole thing on this page.

20plans
4point types
Exceldownload
£0no sign-up

An inspection and test plan says, before the work starts, what will be checked, against what, by whom, and what record will be left behind. Done properly it is the document that settles an argument eighteen months later. Done badly it is a spreadsheet nobody opens after week two.

Download the Excel template 20 plans, one sheet each, plus an index · .xlsx, 51 KB · no sign-up, no email

What an ITP has to contain

Seven columns, and none of them optional:

  1. The activity. One line per thing that gets done and signed for, in the order it happens on site.
  2. What is being checked. The property that matters — line and level, thickness, torque, continuity.
  3. The reference. The drawing, standard or manufacturer instruction it is judged against.
  4. The acceptance criterion. Written so that a pass or a fail is a fact. “Within the specified tolerance under a 2 m straightedge” is a criterion. “Good workmanship” is not.
  5. The point type. Hold, witness, inspection or surveillance — see below.
  6. Who verifies it. A named role, not a company.
  7. The record. The sheet, photograph or certificate that proves it happened.

The four point types

This is where most plans go wrong. A hold point stops the job; a plan with thirty of them will be quietly ignored by week three. Use them where the work genuinely cannot be undone.

Point typeWhat it obliges
HHold pointWork must not proceed past this point until the named party has inspected and released it. The only one with teeth.
WWitness pointThe named party is given notice and may attend. If they do not, work proceeds and the record says so.
IInspection pointInspected and recorded by you. No external release needed, but the record still has to exist.
SSurveillanceMonitored over a period rather than at one moment — a daily pour record, a batch check.

A worked plan: Partitions, Drylining & Fire-stopping

This is ITP-05 from the set, exactly as it comes. Governing standards: BS 8000-8 (plasterboard partitions & dry lining), BS 8214, ASFP guidance. Note how each acceptance criterion could be argued in front of a building inspector, and how the record column names something that will still exist at handover.

No.ActivityWhat is checkedReferenceAcceptance criteriaTypeVerified byRecord
1Setting out of partitionsLine and position to approved layoutApproved GA layoutPositions within tolerance; door openings and structural openings correctISite ManagerSetting-out record
2Framing, head deflection and fixingsStud gauge, centres, deflection head detailSystem spec, BS 8000-8Correct stud gauge and centres; deflection head allowance provided at soffitISite ManagerInspection sheet
3Acoustic / fire insulation installedCorrect density and full fillAcoustic and fire strategySpecified product, tight fit, no gaps at perimeters or servicesISite ManagerPhoto register (pre-close)
4Boarding — layers, orientation and fixingsBoard type, number of layers, staggered jointsSystem certified detailBoard type/thickness per fire test evidence; joints staggered; fixings at specified centresIBuilding ControlBoard inspection sheet
5Service penetrations fire-stoppedEvery penetration sealed with a tested systemThird-party certified detailCorrect product and depth; each penetration photographed, labelled and loggedIFire ConsultantFire-stopping register + photos
6Compartment line continuity above ceilingsCompartmentation continuous to slab soffitFire strategy drawingNo unsealed voids at compartment lines; cavity barriers installedIFire ConsultantPhoto register
7Jointing, taping and finish levelFinish level as specifiedBS 8000-8Specified finish level achieved; no visible fastener heads, ridges or beadingISite ManagerFinish inspection

The twenty plans in the file

One sheet per plan, plus an index and a key to the point types. Delete the ones you do not need.

RefPlanDisciplineGoverning standardsStages
ITP-01Substructure & Below-ground DrainageCivilsBS 8000-1 (excavation & filling), BS 8000-14 (below-ground drainage), BS EN 16107
ITP-02Masonry & External EnvelopeStructure / EnvelopeBS 8000-3 (masonry), BS EN 1996, NHBC Standards Chapter 6.17
ITP-03Roofing & WaterproofingEnvelopeBS 8000-4 (waterproofing), BS 8000-6 (slating & tiling), BS 5534, BS 8217/87477
ITP-04Windows, External Doors & Curtain WallingEnvelopeBS 8213-4, BS 6375, BS 8000-7 (glazing)7
ITP-05Partitions, Drylining & Fire-stoppingFit-outBS 8000-8 (plasterboard partitions & dry lining), BS 8214, ASFP guidance7
ITP-06Plastering & RenderingFinishesBS 8000-10 (plastering & rendering), BS EN 139146
ITP-07Screeds & Floor FinishesFinishesBS 8000-9 (screeds & toppings), BS 8204, BS 5385 (tiling beds)6
ITP-08Carpentry, Joinery & Second FixFit-outBS 8000-5 (carpentry, joinery & general fixings), BS 8214 (fire doors)7
ITP-09Ceramic, Stone & Mosaic TilingFinishesBS 8000-11.1 / 11.2, BS 5385 parts 1–56
ITP-10Decoration & WallcoveringsFinishesBS 8000-12 (decorative works), BS 61506
ITP-11Sanitaryware & Above-ground DrainageM&E / Fit-outBS 8000-13 (sanitary appliances & above-ground drainage), BS EN 120566
ITP-12Hot & Cold Water ServicesM&EBS 8000-15 (hot & cold water services), Water Supply (Water Fittings) Regulations, BS 85587
ITP-13Electrical Installation & TestingM&EBS 7671 (IET Wiring Regulations), Approved Documents P, M and B7
ITP-14Sealants, Joints & AirtightnessEnvelope / FinishesBS 8000-16 (sealing joints with sealants), BS 6213, Approved Document L5
ITP-15Testing, Commissioning & Pre-handoverCross-disciplineProject commissioning specification, Approved Documents F, L and B, Building Safety Act 2022 (HRB)7
ITP-16Suspended Ceilings (MF Grid Systems)Fit-outBS 8290 (suspended ceilings — code of practice), BS 8000-8 (dry lining board fixing)7
ITP-17Dot & Dab DryliningFit-outBS 8000-8 (dry lining board fixing), BS 8212 (dry lining & partitioning using gypsum plasterboard)6
ITP-18SFS External Wall FramingStructure / EnvelopeFIS SFS Specifiers Guide (light gauge steel framing — external wall systems), BS EN 1993-1-3 (design of cold-formed steel), manufacturer system approval8
ITP-19Door Ironmongery (per door set)Fit-outBS 8214 (fire door assemblies — code of practice), BS EN 1935 / BS EN 1154-1155 (hinges and controlled door closing devices), approved door and ironmongery schedule9
ITP-20Internal Door Installation (per door set)Fit-outBS 8214 (fire door assemblies — code of practice), BS 8000-5 (carpentry, joinery and general fixings), approved door schedule9

Mistakes worth avoiding

Filling it in at the end

An ITP signed off in one sitting the week before handover proves nothing, and anybody who has seen a few can tell at a glance. Record the stage on the day it happens or do not record it at all.

Copying the specification into the acceptance column

The specification says what to build. The acceptance criterion says how you will know it was built right. They are different sentences.

One plan for the whole job

A plan per trade package, issued to that package, gets used. A forty-page plan covering everything gets printed once and left in the site office.

When a spreadsheet stops being enough

An ITP in Excel works for one plan on one unit. It stops working when the same fifteen plans have to run across sixty-four flats, when the acceptance evidence is a photograph rather than a tick, and when a failed stage should raise a non-conformance rather than a red cell. That is the job the app does — the same twenty plans, run per unit, with failures that turn into NCRs and a signed record at the end.